Phase One
Concrete Repair and Replacement
Mack and Sons Concrete has accepted the bid to repair and replace the concrete pool deck. Strattonwood was required to complete this work by May 2020.
Nov. 9th a volunteer Strattonwood crew prepared for the concrete by removing awnings, and the bathroom shelter walls.
Nov 12/13 Concrete power washing, grinding and sealing cracks
Dec. 9th Old concrete deck removed
Dec. 17th New concrete deck poured
Pending: Spring 2020 Final sealing coat to be applied. Temperature needs to be over 55 degrees for 3 days to complete work.

Phase Two: Roof Replacement
March 2018: Permit application submitted
September 2019: Permit received
October 2019: Construction bids obtained
November 2019: MillerBuilt Constructions accepted bid for roof replacement.
Jan. 2, 2020 Temporary Fencing/ staging for supplies
Jan 4-10 Electrical and site safety
Jan 10-18: Full demo of roof and wooden supports
Jan 20- Masonry work begins
Feb. 10- Roofing begins
April Construction Update: While work on the pool is paused due to current state guidelines, design and planning continue so we can be prepared for completing work on the pool house remodel.

Volunteers will be needed for a variety of tasks once work is completed to get the pool open as soon as possible.
We will update the website as work progresses. As with all constructions projects dates are subject to change based on weather, and any unforeseen complications with the project. Phase 3 will be updating the bathrooms and assuring ADA compliance